Sunday, 18 August 2013
18.8.2013 Frames Update
Today we went for our usual Sunday visit and we were really impressed with how quick our frames have been put up. To our surprise the house looks so high from the street. Our Roof pitch is 26 degrees and looks hot just watching from the distance.
Thursday, 15 August 2013
Thursday, 8 August 2013
Tuesday, 6 August 2013
Monday, 5 August 2013
5.8.2013 Formwork almost completed
Formwork almost done. Hopefully slab can be poured tomorrow. Spoke to our slab supervisor and next week will be the frames arriving. Its all happening really fast.
Thursday, 1 August 2013
1.8.2013 Piering Done today
Today was another step into our construction phase. I was told last week by our slab supervisor that they will be doing the piers today. We had allocated 70.0 lineal meters of concrete piers in our contract which costed us big dollars. I went this afternoon and to my surprise when we measured we came way under. We ended being 35.0 lineal meters. Heaps of $$$$$ saved.